Phase 1A Capital Improvement Project

Two improvements are proposed for the purpose of addressing RWD #15 system deficiencies in storage and transmission. 

A new 300,000 gallon water tower is proposed along Highway 20 west of Skiatook to replace two existing standpipes that are not able to adequately meet the District's growing demands.  Phoenix Fabricators, of Indianapolis, IN will be constructing the tower, beginning in late 2014.  It is anticipated that the water tower will be complete and ready for operation sometime in the summer of 2015.  

A smaller project involves the construction of 1 1/2 miles of 8-inch PVC pipe along NW 88th Street east of NW 52nd West Avenue.  Pinney Excavation, of Skiatook, has been awarded the contract for this work.